Wallisellen ZH, Switzerland

HHKW Aubrugg
Holzkessel K3

Client: HHKW Aubrugg AG
Location: Wallisellen ZH, Switzerland
Capacity: 1x 6.5 t/h (operation only during heating period), 20 MWth
Duration: 2022 – 2023
Project volume: total approx. 40 million CHF

PDF: HHKW Aubrugg, Holzkessel K3.pdf

Plant description

The aim of this project is to replace the fossil-fuelled district heating boilers from the 1970s with a new K3 wood boiler with a thermal rating of 20 MW. The project started in 2022 based on existing rough studies. The first step was to determine the feasibility. Due to the very tight space conditions in the middle of a motorway junction and the listed building, an in-depth preliminary study in close cooperation with potential suppliers was necessary. Furthermore, the entire planning was performed with the help of a 3D model in order to recognise collisions at an early stage. In terms of process engineering, it was necessary to check how the new plant would be integrated into the existing district heating network during the various heating phases. The in-depth preliminary study, which already has the character of a preliminary project in parts, was completed at the end of 2023. The next step is to assess client funding based on the prepared cost calculation.

Technology

Biomass:
Untreated wood chips

Plant:
Wood firing
Grate firing
Boiler
SNCR
Skimmer
Fabric filter
Back-pressure turbine
Transfer MD steam

Energy utilisation:
Electricity, district heating

Services

General planning for the
K3 wood boiler

  • Feasibility study
  • In-depth preliminary study
  • Enquiries for the main lots with potential suppliers and evaluation of their offers.

Planning with 3D model

  • Entry of the existing plant and the bordering premises
  • Planning of the entire K3 wood boiler, including assembly.

Logistics wood delivery
and transport

  • Review of the additional capacities required for wood boiler K3
  • Planning of the expansion of the transport facilities.

Renewal of compressed air system